APPLICATION UNDER REGULATION 19.2 FOR ADDITIONAL GRANT OF GNA TO STUs
About this approval
This approval is required by State Transmission Utility (STU), who on behalf of intra-State entities including distribution licensees, is applying for additional General Network Access (GNA) to the Inter-State Transmission System in India for the next 3 (three) financial years and is mandated as per the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State transmission System) Regulations, 2022. This approval can be applied once in a financial year (starting from the financial year following the financial year in which GNA Regulations have become effective) during the months of April to September of each financial year.
“Application for additional grant of GNA To STUs under Regulation 19.2” is the applicable form for this approval. The nodal agency for this approval is the Central Transmission Utility (CTU).